The Methodology Behind Gear Train Torque Conversions

Sunday, June 22nd, 2014

      Last time we learned that gear trains are torque converters, and we developed a torque ratio equation which mathematically ties the two gears in a gear train together.  That equation is:

T1 ÷  T2 = D1 ÷ D2

      Engineers typically use this equation knowing only the value for T2, the torque required to properly drive a piece of machinery.   That knowledge is acquired through trial testing during the developmental phase of manufacturing.

      Once T2 is known, a stock motor is selected from a catalog with a torque value T1 which closely approximates that of the required torque, T2.   Then calculations are performed and lab tests are run to determine the driving and driven gear sizes, D1 and D2 which will enable the gear train to convert T1 into the required value of T2.   This series of operations are often a time consuming and complex process.

      To simplify things for the purpose of our example, we’ll say we’ve been provided with all values required for our equation, except one, the value of T2.   In other words, we’ll be doing things in a somewhat reverse order, because our objective is simply to see how a gear train converts a known torque T1 into a higher torque T2.

engineering expert witness gears

      We’ll begin by considering the gear train illustration above.   For our purposes it’s situated between an electric motor and the lathe it’s powering.   The motor exerts a torque of 200 inch pounds upon the driving gear shaft of the lathe, a torque value that’s typical for a mid sized motor of about 5 horsepower.   As-is, this motor is unable to properly drive the lathe, which is being used to cut steel bars.   We know this because lab testing has shown that the lathe requires at least 275 inch pounds of torque in order to operate properly.

      Will the gears on our gear train be able to provide the required torque?   We’ll find out next time when we insert values into our equation and run calculations.